It is really good news for the commuters as the daunting part of the Chinchbhuvan ROB over the railway track on Wardha Road is now ready. As per information, after the cementing work a layer of mastic will be laid. Along with this, the movement of vehicles will commence on this bridge from February 1.
This has faced continuous challenge since the work started in 2019.There was some problems related to the design. And after correcting it, later the problem regarding the height of the crain came up for installing the girders. Due to the reason, the 55 meters long girder was divided into two parts and then it was jointed. Later it faced trouble in getting the block from railways. The works related service road, drain and apron were completed a few months ago. Only the cementing of girder was remaining. Chinchbhuvan ROB is considered as bottleneck of Nagpur-Wardha highway in the city. Besides this, due to the traffic movement from the old narrow ROB, it faces traffic jam more often. The second two lane work of Chinchbhuvan ROB is almost complete. Only upper layer will be laid so that the vehicles passing through it do not skid.Abhijit Jichkar, project director, NHAI stated that after the inauguration the bridge will open for commuters.